Grinding mill: YGM high efficient suspension mill Operating Instruction
Source:http://www.chinaraymondmill.co Author:GreatWall Posted:2015-05-18 Views:
The High-pressure Suspension Mill is an updated of Raymond mill of Great Wall Heavy Industry Company, which used to grind materials which should be non-flammable and non-explosive and have the hardness less than 9.3 in Moh’s scale and humidity less than 6 percent. Compared with Raymond mill with the hardness less than 7 in Moh’s scale, the material can be harder, and the granularity of the end products can be changed from 30 to 425 meshes.
Operating instruction:
Before starting the grinder, check all the doors and make sure that they are tightly closed. Check whether feed opening of jaw crusher is wide enough for the raw materials, adjust and ensure that the speed of the separator is suitable to the required specification of powder-products.
Then start the equipments in the following sequence:
1. Stat the bucket elevator,
2. Start the jaw crusher,
3. Start the screw conveyor of powder collector(OnlyYGM160 ),
4. After the hopper is filled with stuff, start the separator,
5. Start the blower(first without load, after normal operation with load added),
6. Start the grinder, instantaneously to start the electromagnetic vibrating feeder(only YGM160) screw conveyor of powder collector.
Staring procedures:
So the whole set is operating.
“Start”, Elevator→Crusher→Separator→Blower→Grinder→Feeder
Turn
1. Stop the feeder,
2. About one minute later, to stop the grinder,
3. Start the screw conveyor of powder collector(only YGM160),
4. Turn off the separator.
5. Turn off the screw conveyor of powder collector(Only YGM160)
Turn-off procedure:Feeder→Grinder→Blower→Separator→Elevator
(only YGM160) screw conveyor of powder collector.
Remarks: when the material in the hopper reaches a certain amount, the jaw crusher should be switched off first, and then the elevator. This rule depends on the variation of the storing amount.
During the normal operation of the grinder, adding grease is forbidden. To ensure the safety in production and avoid any accident, the grinder should be stopped to check and get rid of trouble when there’s any unusual noise from any parts of the set as well as sudden increase of loading. Take out all the leftovers before starting the machine again, or the motor will burned out because of the oversize current when starting the grinder.
If you want to know the Structure Characteristic and Operation Principle, the working process of main parts, installation operation manual and Commissioning manual, check on them or
CONTRACT US.
Other relevant words: jaw crusher, cone crusher, Roll crusher, Diesel engine crusher
Operating instruction:
Before starting the grinder, check all the doors and make sure that they are tightly closed. Check whether feed opening of jaw crusher is wide enough for the raw materials, adjust and ensure that the speed of the separator is suitable to the required specification of powder-products.
Then start the equipments in the following sequence:
1. Stat the bucket elevator,
2. Start the jaw crusher,
3. Start the screw conveyor of powder collector(OnlyYGM160 ),
4. After the hopper is filled with stuff, start the separator,
5. Start the blower(first without load, after normal operation with load added),
6. Start the grinder, instantaneously to start the electromagnetic vibrating feeder(only YGM160) screw conveyor of powder collector.
Staring procedures:
So the whole set is operating.
“Start”, Elevator→Crusher→Separator→Blower→Grinder→Feeder
Turn
1. Stop the feeder,
2. About one minute later, to stop the grinder,
3. Start the screw conveyor of powder collector(only YGM160),
4. Turn off the separator.
5. Turn off the screw conveyor of powder collector(Only YGM160)
Turn-off procedure:Feeder→Grinder→Blower→Separator→Elevator
(only YGM160) screw conveyor of powder collector.
Remarks: when the material in the hopper reaches a certain amount, the jaw crusher should be switched off first, and then the elevator. This rule depends on the variation of the storing amount.
During the normal operation of the grinder, adding grease is forbidden. To ensure the safety in production and avoid any accident, the grinder should be stopped to check and get rid of trouble when there’s any unusual noise from any parts of the set as well as sudden increase of loading. Take out all the leftovers before starting the machine again, or the motor will burned out because of the oversize current when starting the grinder.
If you want to know the Structure Characteristic and Operation Principle, the working process of main parts, installation operation manual and Commissioning manual, check on them or
CONTRACT US.
Other relevant words: jaw crusher, cone crusher, Roll crusher, Diesel engine crusher